Case Studies

Automotive HVAC Bracket: PA66-GF30 Mold for Tier 1 Supplier

How JBRplas designed and manufactured a 4-cavity PA66-GF30 injection mold for an automotive HVAC bracket — overcoming warpage and achieving PPAP Level 3 approval.

Automotive HVAC Bracket: PA66-GF30 Mold for Tier 1 Supplier
Industry: Automotive Material: PA66-GF30 4-cavity Steel: H13 1,000,000+ shots 28 business days to T1

Project Overview

A European Tier 1 automotive supplier approached JBRplas requiring a precision injection mold for an HVAC bracket — a structural component mounted inside the dashboard assembly that supports the air distribution duct system. The part needed to withstand under-dashboard temperatures up to 110°C continuous, survive 30G vibration testing, and meet PPAP Level 3 documentation requirements.

Challenge: Previous supplier had failed PPAP due to unacceptable warpage on the long flat face of the part — a 180mm unsupported span that distorted by up to 1.2mm after ejection.

Part Specifications

Parameter Specification
Part dimensions 185 × 94 × 38mm
Nominal wall thickness 2.5mm
Material PA66-GF30
Surface finish SPI B2 (non-cosmetic structural)
Critical tolerances ±0.1mm on 4 mounting hole positions
Operating temperature -40°C to +110°C continuous
Annual volume 280,000 pieces

Engineering Approach

Root Cause of Warpage

Our DFM analysis of the previous supplier’s mold data identified two contributing causes:

  1. Gate location — single edge gate placed at one end of the 185mm part caused an asymmetric fill pattern, creating differential fiber orientation in the GF30 material and non-uniform shrinkage across the long axis.

  2. Cooling imbalance — inadequate cooling on the core side of the mold relative to the cavity side caused the part to bow toward the warmer surface during ejection.

Solution: Dual-Gate Valve System + Conformal Cooling

Gating: We designed a hot runner system with two valve gates positioned symmetrically at 60mm from each end of the long axis. This created a balanced, mirror-symmetric fill that neutralized the differential fiber orientation responsible for the previous warpage.

Cooling: We machined conformal cooling channels on the core side that follow the 3D contour of the part — maintaining uniform coolant contact across the entire 185mm span. Core-side water temperature was set 5°C below the cavity side to correct the residual cooling imbalance from the mold base geometry.

Validation: Moldflow simulation confirmed the symmetric fill pattern and predicted residual warpage of 0.18mm on the long face — within the 0.30mm tolerance. Actual measured warpage on T1 parts: 0.14mm.

Tooling Details

Parameter Detail
Mold type 4-cavity hot runner, valve gate
Mold base LKM standard, 500 × 450mm
Core / cavity steel H13, hardened to 50±2 HRC
Runner system Yudo hot runner, 4-drop valve gate
Cooling Conformal on core, conventional on cavity
Surface finish SPI B2, cavity face
Ejection 8× Ø6mm ejector pins per cavity
Mold weight 1,850kg

Timeline

Milestone Duration
DFM report issued Day 3
Mold design complete Day 12
Customer design approval Day 15
Steel ordered and received Day 18
Machining complete Day 24
T1 trial Day 28
T1 samples shipped to customer Day 29
Customer T1 approval Day 38
PPAP submission Day 45
PPAP approval Day 52

Results

Metric Target Achieved
Long-face warpage ≤0.30mm 0.14mm
Mounting hole position ±0.10mm ±0.06mm
T1 lead time 30 days 28 days
PPAP Level 3 approval Required ✅ Achieved
Production Cpk (critical dims) ≥1.67 1.82

The program entered mass production 6 weeks after PPAP approval. The mold has since produced over 420,000 cycles without any maintenance intervention beyond scheduled preventive maintenance at 50,000-shot intervals.


This case study demonstrates JBRplas’s capability to solve complex warpage issues in glass-filled structural automotive parts through systematic DFM, validated Moldflow simulation, and precision hot runner tooling.

Discuss a similar project →